Proposes rerouting the supply duct above the corridor at grid C-4 to clear the new beam.
Today 9:30 AM
Re: RFI #12 — Duct routing at grid C-4
We propose rerouting the 24x12 supply duct 18" north above the corridor ceiling to clear the new W12 beam. No change to airflow or diffuser locations. Please confirm so fabrication can proceed on schedule.
Sprinkler main conflicts with a beam at Level 3, grid F-7. Suggests lowering the main 6".
Today 7:30 AM
RFI #14 — Sprinkler main conflict at Level 3, grid F-7
The 4" sprinkler main as drawn conflicts with the W16 beam. We suggest lowering the main 6" below the beam. Please confirm or advise.
First-pass estimate of $412,800 (HVAC + plumbing). 4 assumptions listed.
Yesterday 3:20 PM
Oak St. Warehouse — First-pass estimate
HVAC: $268,400
Plumbing: $144,400
Total: $412,800
Assumptions: existing gas service is adequate; no seismic bracing; standard working hours; roof curbs by others.